22/05/2025
Quick little update on a couple of worker accomodation houses we have under construction at the mo…
The first has finished plastering and about to be wet sealed before tiling the wet areas…
The second you can see- bricks almost complete, straightening walls prior to starting plastering…
A big thank you to Hadar Homes for cranking these out to budget and ahead of time so far 👍