🚨 CALDERDALE ENERGY PARK (CEP): Planning Timeline.
​The official DCO (Development Consent Order) Timetable for the proposed Calderdale Energy Park wind farm. As a major infrastructure project, this decision bypasses local councils and goes straight to Central Government.
​Here is what the roadmap looks like:
🗓️​July 2026 (Completed but flawed with errors): The Statutory Consultation window closed on July 8th after being extended due to identified data concerns and developer errors.
🗓️​November 2026: The developer plans to submit the application to the Planning Inspectorate, carrying heavy risks if previous flaws aren't fixed.
🗓️​December 2026: A 28-day window for the inspectorate to accept or reject the proposal.
🗓️​Spring/Summer 2027: A formal 6-month Public Examination with open hearings for evidence.
🗓️​Spring 2028: The final verdict will be handed down by the Secretary of State.