01/09/2026
Administrative Approval
INR 14,200 Crore
Technical Details
Total Length – 83.12 km
Total Width – 65.00 m
Railway Over Bridges (ROB) – 2
Tunnels – 11 (Total 12.62 km)
Major Bridges – 17
Interchanges – 9
Current Project Status
Pune-Mumbai Expressway to Pune-Ahmednagar Road connection from Solu Interchange to Vadgaon Shinde (PMC limits) is planned as a priority.
Phase 1 of Stage 1 Solu Interchange to Nirgudi (INR 884.89 crore including GST)
Phase 2 of Stage 1 Nirgudi to Vadgaon Shinde (INR 310.89 crore including GST) DPR is prepared.
Stage 1 – Phase 1 & Phase 2 Land acquisition and forest land clearance are in progress.
Stages 2, 3, 4 Land acquisition proposals for Pune-Ahmednagar Road to Pune-Satara Road have been submitted to the District Collector’s office.
Land Acquisition
As per the Government notification dated 11/09/2023, a Social Impact Assessment (SIA) exemption has been granted for land acquisition across the entire length of the Ring Road, covering a total area of 720.78 hectares.
Phase 1
From Mouje Solu (Taluka Khed) to Vadgaon Shinde (within Pune Municipal Corporation limits), joint land measurement has been completed for the three villages: Mouje Solu, Nirgudi and Vadgaon Shinde. The valuation process for these villages is completed.
Phases 2, 3 and 4
Land acquisition proposals for the following nine villages in Haveli Taluka have been submitted to the District Collector’s Office
Kadamwakvasti
Wadachiwadi
Pisoli
Yewalewadi
Gujar-Nimbalkarwadi
Mangdewadi
Bhilarewadi
Jambhulwadi
Ambegaon Khurd