UPDATE: Data centers in Grant County — what changed this week
In one week, this story moved three times.
Sunday, Aug. 23 — Mayor Ronald Morrell Jr. published the one-page “Project Riverjump” summary himself — more than $2 billion, a roughly 800-acre campus in Marion — and said the deal had become real.
Wednesday, Aug. 26 — the mayor said he will not endorse the proposal, describing it for the first time as “a hyperscale data center in West Marion.”
Thursday, Aug. 27 — in interviews with the Chronicle-Tribune, he named the company: updates “should come directly from Meta or its representatives.” He said no deal has been presented to the city council, that the Oct. 6 meeting is not moving forward, and that there will be no data center development in Marion under his administration. His interviews are the only place Meta has been named — no government document carries it, and the company has said nothing.
https://www.chronicle-tribune.com/news/mayor-walks-away-from-proposed-data-center-project/article_a3f15237-10b5-5a1c-a5b4-84234624e357.html
Also this week: a petition on Change.org asking that no data center be built in Grant County — addressed to the mayor and council members David Cain, Jim Brunner and Brian Cowgill — opened Monday, Aug. 24 and reached 1,084 signatures by Saturday. On Aug. 26 it drew the first response we have found from any Marion council member on the record about the project. “My understanding is that the Data Center is not moving forward,” wrote David Cain of District 6.
https://www.change.org/p/prevent-construction-of-any-data-centers-in-grant-county-indiana
What none of this settles: no application is on file, no site has been named, and a non-endorsement is not a withdrawal — the land agreements the mayor described on Aug. 23 are private contracts his position does not undo.
The residents’ town hall is still on: Monday, Sept. 14, 6 p.m., REAL Community Covenant Church, 1240 S. Adams St.
The full record — every document, recording and land record in this story, each one you can open and check for yourself:
https://ourweek.in/grant-county/reports/data-centers
How we got here — the county's own documents, recordings and land records, from a closed factory in 2022 to a $2 billion sheet circulating in Marion this summer.