06/11/2026
Phase 2 continues to advance steadily and remains on schedule as the project moves from structural completion into sustained interior and exterior finish work. Over the past several months, the team has closed out major envelope activities, including installation of the curtain wall, exterior panels, insulation, and the start of stone façade work. Inside the building, the first floor has transitioned into finish phases with drywall, painting, ceiling grid, lighting, flooring, and wall protection all progressing in sequence. The second floor continues through insulation, drywall, and moisture testing, while MEP rough‑in and sprinkler piping remain active throughout the facility and Penthouse. Generator and transformer installation have positioned the project for permanent power in early June, marking a key milestone for subsequent commissioning activities.