15/07/2025
๐๐ข๐ช ๐ง๐ข ๐๐ฃ๐ฃ๐๐ฌ ๐๐ฆ ๐๐๐ฆ๐ง๐ฅ๐๐๐จ๐ง๐๐ ๐๐ก๐๐ฅ๐๐ฌ ๐ฅ๐๐ฆ๐ข๐จ๐ฅ๐๐ (๐๐๐ฅ):
๐ญ. ๐๐ป๐ถ๐๐ถ๐ฎ๐น ๐๐๐๐ฒ๐๐๐บ๐ฒ๐ป๐- The applicant must undergo an initial assessment to determine the feasibility of installing DER by submitting a letter of intent (LOI) to the DU. The LOI must include information about the total DER capacity, Single Line Diagram (SLD), and location of the DER. The DU will conduct pre-evaluation to determine if the distribution network can accommodate the connection of the DER.
The applicant will be informed if they have passed the initial assessment and will be required to submit necessary documents for the DUโs conduct of Distribution Impact Study.
๐ฎ. ๐๐ถ๐๐๐ฟ๐ถ๐ฏ๐๐๐ถ๐ผ๐ป ๐๐บ๐ฝ๐ฎ๐ฐ๐ ๐ฆ๐๐๐ฑ๐ (๐๐๐ฆ) - The DU will conduct a DIS to determine the impact of the DER installation on the distribution system.
Depending on the results of the DIS, the DU may also conduct a Distribution Assessment Study to determine the additional assets needed to support the connection of the DER.
๐ฏ. ๐๐ป๐ฒ๐ฟ๐ด๐ถ๐๐ฎ๐๐ถ๐ผ๐ป ๐ฅ๐ฒ๐พ๐๐ถ๐ฟ๐ฒ๐บ๐ฒ๐ป๐๐ - Once the DIS and DAS (if applicable) are complete, the applicant will be informed of the interconnection requirements for the energization of their DER installation.
๐ฐ. ๐ฅ๐ฒ๐ป๐ฒ๐๐ฎ๐ฏ๐น๐ฒ ๐๐๐ฅ ๐ฆ๐๐ฝ๐ฝ๐น๐ ๐๐ด๐ฟ๐ฒ๐ฒ๐บ๐ฒ๐ป๐ - The applicant will need to complete the Renewable DER Supply Agreement.
๐ฑ. ๐๐ถ๐ป๐ฎ๐น ๐๐ป๐๐ฝ๐ฒ๐ฐ๐๐ถ๐ผ๐ป - Upon applicantโs compliance with the Interconnection Requirements, the DU will conduct final inspection and install bidirectional meters and Renewable Energy Certificate (REC) meters. The applicant will then coordinate with the DU for the conduct of the functionality tests to ensure that their DER installation is working properly.