When millions are poured, but barely anything stands.
P94-M FLOOD CONTROL PROJECT IN PAMPANGA STALLED AT JUST 5.5% COMPLETION
Photos taken Wednesday show an unfinished flood control project in Sto. Tomas, Pampanga under the Flood Management Program–Construction of Flood Mitigation Structures and Drainage Systems, Upstream Portion of Dalaquitan Bridge Phase 2.
The ₱94-million project began on April 14, 2025, with a target completion date of October 10, 2025. But by July, it was suspended—after only 5.5% progress.