09/12/2026
**A $1.7 Billion Solar Project Is Rising Beside a Texas Coal Plant ☀️⚡**
A major solar development is taking shape at an existing coal-energy complex in Texas—without shutting down the coal operation.
Panamint Capital is developing **Big Rooter Power** at the Twin Oaks energy complex in Robertson County, with plans for roughly **1.2 gigawatts of solar capacity**. The existing 310-megawatt Twin Oaks coal plant and nearby lignite mine are expected to continue operating.
The location offers a major advantage: the site already has electricity infrastructure and grid connections, potentially making it easier to add new generation than starting from scratch on undeveloped land.
The first phase, **Big Rooter West**, will have about 491 megawatts of solar capacity and is scheduled to begin commercial operations in August 2028. A second 658-megawatt eastern phase is planned for operation in 2029.
The project is expected to create more than **800 construction jobs**, with First Solar supplying around **two million panels manufactured in the United States**. The broader 10,000-acre complex is also being developed for battery storage and data-center capacity.
It’s an unusual energy transition story: **solar power is being added directly beside an operating coal facility**, allowing an old energy site to support a new source of electricity without immediately replacing the existing one.