09/02/2026
Freebie of the Week in News:
Rolling Cedar, LLC: ‘We are not attached to any data centers, we’re just a power plant’
By Cinthia Descloux
New natural gas-fired plant in the works, estimated to employ 427 at peak, then 15 full time permanent jobs when completed
Rolling Cedar LLC’s Rolling Cedar Power Plant Project, a partnership developed between 8 Rivers (of Durham, North Carolina) and Kindle Energy (of Princeton, New Jersey), will not be supplying any data centers with the electricity they create once the project is up and running, according to 8 Rivers President / CEO Damian Beauchamp.
Beauchamp declined to release how much the project will cost, citing they “still have bids out.”
However, the U.S. Energy Information Administration (EIA) gives a baseline figure of $836 per kW for a utilityscale H-Class simple-cycle gas turbine (source: Capital Cost and Performance Characteristics for Utility-Scale Electric Power Generating Technologies).
Estimates for building a natural gas-fired power plant of this size and producing approximately 430-megawatts could cost somewhere between $280-$515 million for engineering, procurement and construction, according to EPC (Engineering, Procurement and Construction), depending on actual costs at the time.
Beauchamp and representatives from the two companies were in Glenrock, Douglas and Rolling Hills Monday and Tuesday to hold open houses in those communities and to answer questions from the public.
“We are not attached to any data centers – we’re just a power plant. Everyone is chasing after data centers, so we decided instead to focus on the gaps that weren’t being filled,” Beauchamp said Monday morning following a presentation at Eastern Wyoming College in Douglas. “We hope to be interconnecting with . . . (RMP) substations, but we don’t have anything (in place) now.”
Construction on Rolling Cedar is expected to begin in May, 2028. The plant is estimated to move into commercial operations between June, 2030 and early 2031 Beauchamp stated.
DETAILS
The Rolling Cedar power plant is planned as an approximately 430MW, simple cycle gas turbine natural gas-fired electric generation facility, located on a permanent footprint north of the Dave Johnston power plant and on Rocky Mountain Power-owned land, Beauchamp said, approximately three miles east of Glenrock in Converse County.
It’s also expected to be mostly water-free, Beauchamp stated at the Douglas meeting, saying water would likely only be needed for sinks and bathrooms.
However, they would like access to limited water, if possible, during the high temperatures in summer months.
“The plant will be water-free, as we’ve planned for it. We’d like to have water during the hottest days (for operations and MW output),” he explained.
In a letter to the Wyoming Department of Environmental Quality dated Aug. 12, representatives explained the project will include the installation of natural gas combustion turbine generators, emissions control equipment, underground natural gas pipelines and related infrastructure. During the construction period of approximately 26-months, temporary roads, lay down areas and workspace will also be established within the project site boundary.
Access to the site will be via WY0 95 from the north and Tank Farm Road from the south. A combination of existing private access roads will be used for construction and operations.
EMPLOYMENT
Beauchamp said there will be approximately 15 permanent jobs associated with the power plant once it’s up and running. The workforce at its high is estimated at 427 jobs during a three-to-fourth month construction peak, with an average of about 265 people to be employed over the construction timeline.
“Our goal is to become part of the (Converse County) community . . . We want to tap into the local workforce first, check into colleges, then Casper,” Beauchamp noted.
WHAT’S NEXT
At this time, the final project design is underway. Beauchamp said geo-technical work is going on now at the site.
Rolling Cedar, LLC, is applying for a Wyoming Industrial Development Information and Siting Act Section 109 permit to construct and operate the plant.
According to the project’s fact sheet, Rolling Cedar will be a significant capital investment in Wyoming and will support the Converse County and Wyoming (economies) through the creation of construction and operations employment opportunities, as well as the purchase of regional goods and services, when possible. The complete economic benefits and anticipated impacts from the project are still being determined and will be fully analyzed through the permitting process.
The submittal of a Converse County Notice of Industrial Activity is anticipated by the first quarter of 2027.
A permit for this project is not required by Converse County, as the county is not zoned, according to Commission Chairman Jim Willox. He said Road & Bridge will be partnering with Rolling Cedar when it comes to working on roads.
“We’ve already started a lot of work with Road & Bridge,” Beauchamp confirmed.
The permit application to the Industrial Siting Council is planned for submittal this fall, with a public hearing tentatively planned for the first quarter of 2027.
Send a message to learn more