10/09/2025
HUNTSVILLE – Big changes will be coming to the intersection of IH 45 and FM 1374/Montgomery Road in Huntsville as crews prepare to demolish the existing bridge and build a brand-new one. To keep traffic flowing during construction, a temporary roundabout-style traffic pattern will be introduced using the newly built U-turn bridges.
The main bridge that crosses IH 45 at FM 1374 will be removed and replaced. While this work is underway, drivers will use a roundabout-style configuration (see map below) to move through the intersection. This setup will rely on the recently completed U-turn bridges to keep traffic moving safely and efficiently. Signage will be in place to guide drivers through the intersection.
Key Dates to Know:
• Saturday, October 11, 2025 – Roundabout Traffic Pattern Begins
o Lane closures on IH 45 frontage roads and FM 1374 from 8 a.m. to 5 p.m.
o New traffic pattern goes into effect
• Friday, October 17, to Sunday, October 19, 2025 – Bridge Demolition Weekend
o Full closure of IH 45 main lanes from 8 p.m. Friday to 10 p.m. Sunday
o IH 45 Northbound traffic will exit at Exit 114 and re-enter north of Smither Drive
o IH 45 Southbound traffic will exit at Exit 115 and re-enter south of FM 1374
Construction of the new bridge is expected to be completed by late January 2026. Once open, traffic will return to a more conventional flow across IH 45.
TxDOT appreciates everyone’s patience and cooperation as we work to improve infrastructure and safety in our community. Please drive carefully and follow posted signs during this transition.