Data Center Permits Detail Proposed Air Quality Footprint
SAN ANGELO, TX - Beacon Data Centers, appearing as Westline TX Holdings, have submitted their air quality permit to the Texas Commission for Environmental Quality (TCEQ) for their proposed construction in Tom Green county.
According to the application, they plan to generate electricity for the data center campus on-site, using internal combustion engines powered by natural gas to power the multi-gigawatt facility.
They anticipate an annual carbon dioxide emission of 1,177 tons per year, which according to the EPA is equivalent to a little over 132,000 gallons of gasoline consumed, or 1.3 million pounds of coal burned.
They also state that they plan to use on site diesel power generation as a backup, which would likely run for at least a half hour per month to ensure function, Beacon officials have said.
The proposal reads: "The permit will authorize construction of the data center and energy facility. The data center will not rely upon power from the grid, but rather, will operate using electricity that is generated onsite by the energy facility using natural-gas reciprocating internal combustion engines (RICE)."
It concludes: "This application is being processed in an expedited manner, as allowed by the commission’s rules in 30 Texas Administrative Code, Chapter 101, Subchapter J.”
According to that statute "if the applicant demonstrates that the purpose of the application will benefit the economy of this state or an area of this state" they may request an expedited approval process, for which the "executive director may add a surcharge for an expedited application."
A surcharge which "will be remitted in the form of a check, certified check, electronic funds transfer, or money order made payable to the Texas Commission on Environmental Quality (TCEQ)."
At a particularly fierce County Commissioners meeting last month, an officer for Beacon was present to answer questions from the court and the general public, having been asked to appear following a push to impose a moratorium on data center construction in Tom Green County's 4th precinct.
For the full article: visit the link below.
SAN ANGELO, TX - Beacon Data Centers, doing business as "Westline TX Holdings" have submitted their air quality permit to the Texas Commission for Environmental Quality