Celebrating my 4th year on Facebook. Thank you for your continuing support. I could never have made it without you. πŸ™πŸ€—πŸŽ‰

Eskom Limpopo employees in the Capricorn District have installed load-limiting devices in Mokopane, Zebediela, and Lebow...
24/07/2025

Eskom Limpopo employees in the Capricorn District have installed load-limiting devices in Mokopane, Zebediela, and Lebowakgomo.

Load limiting is a demand management solution that allows Eskom to limit the maximum output power of a smart meter for a predefined period, with the purpose of controlling demand in consultation with customers. Customers are encouraged to switch off high-consuming appliances, such as geysers, stoves, washing machines, and pool pumps during this period. If such appliances are not switched off, the meter will disconnect the supply for a configured period and display the reasons for the disconnection. In this case, the meter will display β€œPower overload."

UNIT 4 AT MEDUPI POWER STATION RETURNS TO SERVICE Eskom says Unit 4 of its Medupi power station has been successfully re...
07/07/2025

UNIT 4 AT MEDUPI POWER STATION RETURNS TO SERVICE

Eskom says Unit 4 of its Medupi power station has been successfully returned to service, eight months ahead of its original schedule, adding 800 megawatts to the national grid.

The power utility said this milestone strengthens South Africa’s energy security and enhances the stability of the electricity supply.

LOAD REDUCTION ALERT ⚠️ Eskom will implement load reduction in some parts of Mopani District on Friday, the 9th of May 2...
09/05/2025

LOAD REDUCTION ALERT ⚠️

Eskom will implement load reduction in some parts of Mopani District on Friday, the 9th of May 2025 from 17 : 00 to 19 : 00

1. GREATER LETABA MUNICIPALITY

πŸ“Œ Ga - Matshwi, Ga - Mabulana, Ga - Modjadji, Mokwasele, Ga - Mothibeki, Modubung, Shotong, Mohlakamosoma, Meidengen, Molematse, Kgapane, Ga - Raphahelo, Geradine, Mangulwane, Muwaweni, Tshabelani, Ga - Sekgopo, Morebeng, Soekmekaar, Munnik, Ga - Phooko, Uitval, Blinkwater.

2. GREATER TZANEEN MUNICIPALITY

● LENYENYE AREAS

πŸ“Œ Mogoboya, Khujwana, Lenyenye, Marumofase, Maake, Matselapata, Myakayaka, Khopo, Moime, Twanano, Khujwana, Pharare, Mashiloane, Mogapeng, Rita, Ramalema, Shiluvane, Uplands, New Khopo, Dan Extension, Ndhuna Mbhalati, Rhulani, Lusaka, Hoveni, Sebela, Moshate, Thabina Valley, Phepeng

● NWA'MITWA AREAS

πŸ“Œ Nyakelani, Xihoko, Mandlakazi, Mbekwana, Fofoza, Babanana, Musiphani, Mavele, Mookgo, Morapalala, Rikhotso, Ka Mswazi, Nkambako, Malobane, Merckry, Maweni, Runnymede, Mbyepelong and Joppie

● BOLOBEDU SOUTH AREAS

πŸ“Œ Bokuta, Fobeni, Jokong, Khwekhwe, Kubjana, Motupa, Sebabane, Mopye, Moleketla, Thako, Lerejeni, Mapitule, Marirone, Mohlakong, Relela, Thapane, Sethone, Pjapjamela.

3. GREATER GIYANI MUNICIPALITY

πŸ“Œ Bambeni, Bode, Ka - Dzingidzingi, Ka - Siandane, Sikhunyane, Kremetart

4. MARULENG MUNICIPALITY

πŸ“Œ Lorraine, Sofaya, Worcester, Dublin, Botswana, Sedawa, Mametja, Ballon, Finale, Diphuti, Kubjaname, Portsmouth, Dinyapong, Ga - Mabina, Ga - Sekororo, Calais, Bordox,

5. BA - PHALABORWA

πŸ“Œ Namakgale, Tipeng, Mashishimale, Ga - Makhushane, Croc Branch, Schalk

www.tzaneenvoice.co.za

ESKOM ANNOUNCES STAGE 2 LOADSHEDDING Eskom says Stage 2 loadshedding has been implemented from 16:00 today and will rema...
24/04/2025

ESKOM ANNOUNCES STAGE 2 LOADSHEDDING

Eskom says Stage 2 loadshedding has been implemented from 16:00 today and will remain in effect until 05:00 tomorrow.

POWER OUTAGE ALERT | Eskom Technicians on Site at Motseketla Section in Ga-SekgopoEskom technicians are currently on-sit...
06/03/2025

POWER OUTAGE ALERT | Eskom Technicians on Site at Motseketla Section in Ga-Sekgopo

Eskom technicians are currently on-site at Motseketla Section in Ga-Sekgopo to repair the transformer and restore power. The team is working to resolve the issue as quickly as possible.

LOADSHEDDING TO DOWNGRADE TO STAGE 2 Stage 4 loadshedding will continue to be implemented until 5:00 AM on Tuesday. Ther...
24/02/2025

LOADSHEDDING TO DOWNGRADE TO STAGE 2

Stage 4 loadshedding will continue to be implemented until 5:00 AM on Tuesday. Thereafter, loadshedding will be reduced to Stage 2 until further notice.

Eskom says this decision follows the successful recovery of eight out of ten generation units and the restoration of 3 808MW from units that tripped over the weekend, with an additional 1 146MW expected to be recovered overnight.

"While the recovery of the emergency reserves is progressing well, further replenishment is required to reach sufficient levels.

These positive developments support our ongoing focused efforts to stabilise the power supply and ensure reliability," Eskom said in a statement on Monday night.

Currently, unplanned outages are at 13 690MW, which is 690MW higher than our summer outlook base case of 13 000MW. Ongoing planned maintenance stands at 7 245MW, in alignment with our summer period maintenance strategy, that is at increased levels in order to prepare for winter and meet licence and regulatory requirements.

Eskom says it will provide the next update on Tuesday, 25 February 2025, or as soon as any significant changes occur.

ESKOM RAMPS UP LOADSHEDDING TO STAGE 6 Eskom has announced that Stage 6 loadshedding was implemented at 1:30am  due to m...
23/02/2025

ESKOM RAMPS UP LOADSHEDDING TO STAGE 6

Eskom has announced that Stage 6 loadshedding was implemented at 1:30am due to multiple unit trips at Camden Power Station and will continue until further notice.

The power utility says this measure followed the implementation of Stage 3, necessitated by multiple unit trips at Majuba Power Station and a unit trip at Medupi that resulted in a loss of 3 864 MW in generation capacity, while planned maintenance accounted for 7 506 MW. Additionally to replenish emergency reserves and prepare for the week ahead.

A media briefing will be held today at 11:00 to provide more details and updates on the power system.

Find schedules for your area on WhatsApp group: https://chat.whatsapp.com/ISdsG6wFNtk3jRwblnc7od

ESKOM ALERT | LOAD SHEDDING RETURNS After 20 days of uninterrupted power supply, Eskom has announced that load shedding ...
22/02/2025

ESKOM ALERT | LOAD SHEDDING RETURNS

After 20 days of uninterrupted power supply, Eskom has announced that load shedding will begin tonight, February 22.

In a statement, Eskom cited temporary setbacks as the cause of the sudden power cuts.

Stage 3 load shedding has been implemented from 17:30 on Saturday evening with no specified end date.

PUBLIC NOTICE | ZERO BUYER CAMPAIGN Date: Saturday, 22 February 2025 Venue : Rita Primary School Time: 09 : 00 to 15 : 0...
20/02/2025

PUBLIC NOTICE | ZERO BUYER CAMPAIGN

Date: Saturday, 22 February 2025
Venue : Rita Primary School
Time: 09 : 00 to 15 : 00

POWER OUTAGE ALERT | A broken conductor to RJB has led to the whole of Mohlaba cross and the whole of Burgersdorp withou...
06/02/2025

POWER OUTAGE ALERT |

A broken conductor to RJB has led to the whole of Mohlaba cross and the whole of Burgersdorp without electricity.

Eskom says it is aware of the outage and already dispatched Technicians to work on site

Will keep you updated as we don’t know the restoration time

UNPLANNED POWER OUTAGE | πŸ“Œ THABAZIMBI There is an unplanned power outage affecting several areas due to a tree located o...
06/01/2025

UNPLANNED POWER OUTAGE | πŸ“Œ THABAZIMBI

There is an unplanned power outage affecting several areas due to a tree located on the overhead power line at Regorogile Extension 5. The following areas are impacted:

- Regorogile Extensions 5 & 6
- Thaba Mall
- Thaba-Junction
- Industrial Area
- SASSA
- Thabazimbi Hospital Areas

The maintenance team is currently assessing the situation and will take immediate action to resolve the issue.

We will keep you updated on the progress and estimated time for power restoration. For further inquiries, please contact 0837032804.

Address

Tzaneen

Telephone

+27734187356

Website

Alerts

Be the first to know and let us send you an email when Limpopo Eskom Updates posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Limpopo Eskom Updates:

Share